Retention calculator — the pot, the claim cut, and the release dates

On a 1,000,000 contract at 10% retention, the pot is 100,000, a claim of 120,000 gives up 12,000, and with half released at completion, 50,000 comes back then and 50,000 after the defects period. Enter your own contract figures below — free, no signup.

Your quantities

Retention pot (the ceiling)–
Held from this claim–
Released at completion–
Released after defects period–

How the retention money is worked out

Retention is a percentage of every certified claim, held back by the client as security for completion and defects. The pot — the most that can ever be held — is simply the contract value multiplied by the retention percentage. Each progress claim gives up the same percentage of its certified value: claim 120,000 at 10% and 12,000 is held, 108,000 is what the certificate actually pays.

Release is usually in two slices. The first comes at practical completion — often half the pot, but the share is whatever the contract says — and the balance after the defects liability period ends. This calculator applies your three percentages to your two money figures; it does not invent terms. The percentages in a real job live in the signed contract, and where a cap on total retention applies, the contract states that too — check yours before you rely on any figure here.

Two contract shapes change the picture this calculator draws. Some contracts let the contractor swap the held cash for a retention bond or bank guarantee — the client keeps its security, the contractor frees the cash, and the pot becomes a fee instead of a freeze. And where retention flows down a subcontract chain, each tier may hold from the tier below on its own dates, which are not automatically the dates on which the tier above releases. Neither shape is a default: both live or die by the signed wording.

Running these jobs? Masonry & Plaster

How to use the retention calculator

  1. Enter the contract value — the full agreed sum, in your contract's currency.
  2. Enter the retention percentage your contract sets — 5% and 10% are the common Gulf figures.
  3. Enter the share of the pot released at practical completion, again from your contract (often half).
  4. Enter one progress claim's certified value to see what that claim gives up.
  5. Read the four figures: the pot, this claim's cut, and the two release slices.

Retention on a 1,000,000 contract, worked through

The pot: 10% of 1,000,000 is 100,000 — the ceiling on what the client can hold across the whole job, reached claim by claim.

The claim cut: a certified claim of 120,000 loses 10%, so 12,000 joins the pot and the certificate pays 108,000. The releases: half the pot, 50,000, returns at practical completion, and the remaining 50,000 after the defects period — which is why the guide to retention money insists the release dates belong in a diary, not in memory.

A second shape, at the gentler rate common on larger contracts: a 2,400,000 contract at 5% gives a pot of 120,000 — half the rate of the first example, on more than double the value, and still the larger pot. A certified claim of 300,000 gives up 15,000 and pays 285,000; at a 50% completion release, 60,000 returns at practical completion and 60,000 after the defects period. Run the two examples side by side and the lesson stands out: the percentage is the headline, but the pot is the number your cash flow actually feels.

The common retention shapes, as a sense-check

Shapes seen on Gulf contracts (your contract decides)

ShapeRetentionRelease
Standard subcontract10% of each claimHalf at completion, half after defects
Smaller works package5% of each claimHalf at completion, half after defects
Maintenance-style contract5% of each claimAll after the defects period

Retention habits that protect the pot

  • Record the two release dates the day the contract is signed — retention is lost by forgetting far more often than by dispute.
  • Track the pot claim by claim in the same place you track certificates; a pot you cannot state in one number is a pot you will argue about.
  • Chase the completion release with the taking-over certificate attached — the paper is what unlocks the money.
  • Price retention into your cash flow, not your margin: the money is yours, it is just late — plan the gap or it plans you.
  • On subcontract work, compare the release dates you are given with the dates your own client works to — back-to-back retention is negotiable before you sign, and almost never after.
Questions

Retention Calculator

Is retention the same in every contract?+

No. The percentage, the cap and the release points are contract terms — 5% and 10% are common in the Gulf and half-at-completion is a common shape, but your signed contract is the only version that counts. This calculator applies your terms; it does not set them.

Does the calculator handle a retention cap?+

The pot figure IS the simplest cap — contract value × percentage. Some contracts cap retention at a fixed sum or stop deducting part-way through; if yours does, compare the pot here against the cap and work from the lower figure.

Which currency does it use?+

Yours. The arithmetic is identical in dirhams, riyals or any other currency, so the calculator takes plain numbers and returns plain numbers.

Can InstaJack track the pot for me?+

Yes — retention held and released is part of the claim record in the app, so the pot builds itself from your certified claims instead of living in a spreadsheet. The calculator here stays free either way.

Can retention be swapped for a bond?+

In some contracts, yes: the contractor provides a retention bond or bank guarantee for the held amount, and the client releases the cash against it. The client keeps the same security, and the contractor trades a frozen sum for a bond fee. It exists only where the contract allows it — ask before signing, because adding it afterwards needs the client's agreement, not just a form.